Further work commences on Phase 1
The Belfast Streets Ahead Project continues to move forward with work commencing in January 2008 on Area 3, ( Fountain Street, College Street and Fountain lane).
The Fountain Street and College Street elements of the project will take approximately 9 months to complete with work scheduled to finish in September 2008.
Work to Fountain lane will start in July and is scheduled for completion in November 2008.
|