Work continues on Phase 1

Ann Street -  work has now recommenced on Ann Street.
Work is being carried out in conjunction with NIE who are carrying out a major upgrade to their infrastructure. As a result of these additional works, completion date completion date for the Belfast Streets Ahead work is now expected to be late 09.
Queen Street - Work commenced end of June 08 and is scheduled for completion May 09
Fountain Lane - Work commenced in July 08 and is scheduled for completion November 08
Castle Street - Work due to commence in September 0 and is scheduled for completion July 09